Get New 2022 Valid Practice To your AACE-PSP Exam (Updated 120 Questions)
AACE Certification AACE-PSP Exam Practice Test Questions Dumps Bundle!
How to book the Planning & Scheduling Professional (PSP) Exam
Follow the steps mentioned below to book the Planning & Scheduling Professional (PSP) Exam:
- Step 1: Visit the AACE’s website by clicking here
- Step 2: Create a new account or log in to an existing account
- Step 3: Select your professional exam
- Step 4: Complete the required course and take PSP practice test
- Step 5: Fill the application and submit all required documents
- Step 6: Schedule your exam by following the instructions on the website
The benefit of obtaining the Planning & Scheduling Professional (PSP) Exam Certification
Certifications offered by the Association for the Advancement of Cost Engineering (AACE) have been a mark of distinction for more than thirty years, and more and more employers are requiring these certifications as a prerequisite for jobs. PSP is one of AACE’s commonly recognized qualifications that cover subjects related to the preparation and scheduling of projects. Obtaining an AACE qualification also leads to greater peer acceptance and increases job and income prospects.
While a licensed professional engineer is usually considered “certified” in any field in which he or she works (imposing self-discipline to not “practice outside one’s areas of expertise”), for both licensed engineers and unlicensed technicians, the national mood is to require certification in specialty disciplines. A welcome response to the increased power of our software tools in education and training in theory as well as practice and qualification regulated by our professional societies, such as AACE (with the PSP exam noted above and PMI (with the PMI-SP exam).
NEW QUESTION 21
Activity C is a
- A. 1-day activity.
- B. Continuous activity.
- C. Milestone.
- D. Contentious activity.
Answer: C
NEW QUESTION 22
Which is NOT an industry-recognized methodology for quantifying critical delay?
- A. Gantt Chart.
- B. Periodic Windows.
- C. Collapsed As-Built.
- D. Time Impact.
Answer: A
NEW QUESTION 23
Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?
- A. The activities occur in series with a 15-day lag.
- B. These activities are concurrent with Activity 4001 starting 15 days earlier than the start of Activity 3001.
- C. The activities run concurrently.
- D. These activities are concurrent with Activity 4001 starting 15 days after the start of Activity 3001.
Answer: A
NEW QUESTION 24
Of the following update procedures, which is the least important in achieving an accurate forecast for completion of a construction schedule?
- A. Estimating remaining durations of activities.
- B. The correct recording of actual start dates.
- C. Entering the time impacts of delays and change orders.
- D. Making "downstream" logic revisions as required.
Answer: D
NEW QUESTION 25
If after calculating a schedule an activity exhibits negative total float, which of the following is certain? The activity
- A. Has yet to be completed.
- B. Was completed in the past.
- C. It is on the critical path.
- D. Is a milestone.
Answer: A
NEW QUESTION 26
Which of the following will always describe the critical path? The path with
- A. Zero float.
- B. The longest duration through the network.
- C. Negative float.
- D. The shortest duration and negative float.
Answer: A
NEW QUESTION 27
Which of the following is NOT input data to the construction planning process?
- A. The contract
- B. Bonding capacity of subcontractors
- C. Input from the contractor
- D. Input from the owner
Answer: B
NEW QUESTION 28
What method offers the best chance of the schedule being used effectively to implement the project in the field?
- A. Issue detailed schedule updates as frequently as possible.
- B. Obtain consent and agreement to the schedule from the key project personnel.
- C. Allow large time contingencies on milestones and completion deadlines.
- D. Include detailed and stringent set of scheduling specifications in the contract.
Answer: B
NEW QUESTION 29
When resource leveling craft labor for a critical path schedule, the scheduler
- A. Need not consider its effects, as it is a theoretical concept with limited application to construction projects.
- B. Must consider breaks in continuity of work for subcontractors, thereby possibly incurring additional subcontractor mobilization and demobilization costs.
- C. Can depend on the results of the resource leveling operation to reflect a useful realignment of all schedule activities without 'further analysis.
- D. Need only consider the non-union crafts persons.
Answer: C
NEW QUESTION 30
If all other work proceeds according to the Baseline plan, how many times will the critical path change?
- A. 2.
- B. Does not change.
- C. 1.
- D. 3.
Answer: B
NEW QUESTION 31
These are the activities on the critical path:
- A. A, C, E, & H.
- B. A, D, & I.
- C. A, B, F, & J
- D. A, B, G, & H.
Answer: D
NEW QUESTION 32
Identify the minimum project duration.
- A. 21 months.
- B. 20 months.
- C. 19 months.
- D. 16 months.
Answer: B
NEW QUESTION 33
The activity with the most total float is:
- A. Activity F.
- B. Activity I.
- C. Activity C.
- D. Activity D.
Answer: B
NEW QUESTION 34
If someone wanted to constrain a project's end date so that any project slippage would cause negative float, they would do so by using
- A. Start-no-later constraint on the first activity
- B. Finish-no-earlier constraint on the first activity
- C. Finish-no-later constraint on the last activity
- D. Finish-no-earlier constraint on the last activity
Answer: C
NEW QUESTION 35
Why does activity 1001 have two successor activities?
- A. Because the late finish of 1001 and the late start of 7001 require two successors
- B. Because the problem could not effectively work with only one successor
- C. Because there are two defined logic paths for the work
- D. Because the duration of activities 2001, 2002 and 200.f require two successors
Answer: C
NEW QUESTION 36
You are developing a detailed critical path schedule for a proposed petrochemical plant. The schedule will become a part of the project baseline document, which will be sent to the company's board of directors for its consideration. What document or resource is likely to be MOST valuable in determining the schedule's work activity durations?
- A. The Petrochemical Industry New Plant Task Duration Handbook.
- B. The cost estimate for the plant prepared by your firm's estimating department.
- C. Industry publications.
- D. Critical path schedules prepared by you for similar completed projects.
Answer: D
NEW QUESTION 37
What is the workweek period for this project?
- A. Sunday through Saturday
- B. Sunday through Friday
- C. Monday through Friday
- D. Monday through Saturday
Answer: A
NEW QUESTION 38
Which of the following phases does NOT describe the commonly accepted construction life cycle?
- A. Installation phase.
- B. Claims and disputes phase.
- C. Planning and design phase.
- D. Turnover and start-up phase.
Answer: C
NEW QUESTION 39
What is the primary difference between the arrow diagramming method (ADM) and the precedence diagramming method (PDM)?
- A. ADM is manual CPM calculations, while PDM is computerized.
- B. ADM is limited to finish-to-start logic relationships, while PDM is not.
- C. PDM is a bar chart with network logic, while ADM is a pure logic network.
- D. ADM uses arrows, while PDM uses boxes.
Answer: B